SoftBank cancels gas turbine orders, faces $3.7 billion hit

The Japanese investment group has cancelled gas turbine reservations it had made for AI data centers. It also denied Elon Musk's claim that it defaulted on contracts.

· · 2 min read
Construction equipment and workers at a groundbreaking site in front of SoftBank Group signs and a hanging American flag

Japanese technology investor SoftBank has cancelled the remaining gas turbine capacity it had reserved to power AI data centers, a move that will cost the company $3.7 billion in earnings.

The decision came right after SoftBank's chief financial officer responded to Elon Musk's claim that the company had defaulted on turbine blade contracts. The company stresses that the cancellation was voluntary and that no default exists.

A reservation bigger than Connecticut

According to reports citing sources familiar with the matter, SoftBank had reserved a large share of global gas turbine manufacturing capacity for itself by early 2026. The reserved turbines totaled more than 13 gigawatts, which is more than the entire generating capacity of the US state of Connecticut and equivalent to more than six Hoover Dams.

Founder and CEO Masayoshi Son is said to have believed this capacity would be vital to the company's future earnings potential. Gas turbines convert natural gas into the electricity data centers consume, and orders must be placed years before the equipment is needed. SoftBank told investors the orders were placed in anticipation of a possible equipment shortage.

The Ohio project and a change of course

SoftBank has plans for a 9.2-gigawatt power plant in Ohio. Construction is expected to begin in early 2027, the facility is estimated to cost $33 billion, and it would supply an eight-gigawatt data center next door. That data center would be leased to OpenAI, though reportedly only after Nvidia entered talks to guarantee roughly $250 billion in financing for the project.

The company originally intended to use the turbines for future gas-fired plants but has now changed direction. The large orders were placed on the assumption that demand would far outstrip supply, which could have given SoftBank an advantageous position in the AI-driven data center buildout by securing critical components. The reservations were not cheap, however: turbine makers typically charge customers tens of millions of dollars per gigawatt.

GE Vernova cancellations and the dispute with Musk

SoftBank cancelled its remaining reservations with turbine supplier GE Vernova and is also terminating contracts for orders that it was already too late to reverse. The company told investors the orders had been placed in anticipation of a shortage, but the outcome suggests that expectation was somewhat overstated.

Elon Musk had claimed in a post on X that SoftBank defaulted on turbine blade contracts. SoftBank's CFO, Yoshimitsu Goto, said the claim was entirely false and that no such default had occurred. SoftBank maintains that the cancellation was its own choice.

Add as a preferred source on Google See Merhabyte stories more often in Top Stories on Google Search.

Comments

No comments yet. Be the first to comment.

Leave a comment

We do not ask for your e-mail. Comments are checked automatically before they go live.

Up next

All →