Anthropic to Spend $3.4 Billion on 1.7 GW of Gas Generators

Claude developer Anthropic is taking over OnePWR Solutions' generator orders with Caterpillar, securing 1.7 GW of capacity for its data centers.

· · 3 min read
Aerial view of a construction site beside a large facility, with a crane, vehicles, and cooling units

Anthropic, the AI company behind Claude, has signed a $3.4 billion deal for gas-fired generators to meet the power needs of its data centers. According to the information available, the agreement covers a total of 1.7 gigawatts (GW) of generating capacity and was reached in late September.

Anthropic is not acquiring Texas-based supplier OnePWR Solutions. Instead, it is taking over OnePWR's existing generator orders with Caterpillar. The deal also includes the engineering and construction work needed to install the equipment.

Taking over existing orders

The orders in question were placed roughly two years ago but needed additional financing. By assuming them, Anthropic avoids starting from scratch. Otherwise, it would have had to wait for Caterpillar to fit a new, large order into its production schedule.

The timing matters because orders for large gas turbines and generators are piling up, and manufacturers are struggling to keep pace, particularly with demand from AI companies.

A supply gap in the turbine market

According to reported figures, global turbine orders exceed 100 GW, while manufacturing capacity is estimated at 60 to 70 GW. In the US, average delivery times have reached six years, with some prospective orders stretching to 2030 or 2031.

Against that backdrop, Anthropic's move stands out as an attempt to skip the long waiting list and gain quick access to power capacity. Because the deal also covers engineering and construction, the company is securing not only the generators but the services needed to install them.

Similar moves across the industry

Anthropic is not alone. Elon Musk's xAI turned to gas-based generation to bring large computing facilities online without waiting for a grid connection. The company installed eight converted General Electric jet turbines at a data center in Mississippi, each capable of producing up to 50 MW, for a total output potential of 400 MW. The setup drew the attention of the Southern Environmental Law Center, which has challenged its emissions permits.

Musk's companies are also moving into equipment manufacturing. In August, one of Musk's companies reportedly brought turbine blade production in-house; Musk describes component manufacturing as one of the biggest bottlenecks in generator deliveries, and some turbine blades are said to take 60 to 90 weeks to produce. In July, SpaceX acquired APR Energy, which has a fleet of trailer-mounted gas and diesel generators capable of producing more than 1 GW.

The approach is not unique to Musk's companies. OpenAI took a similar path for the first Stargate data center in Abilene, Texas. Crusoe, which developed the site, reportedly acquired 29 GE Vernova LM2500XPRESS gas turbines of 34 MW each; together, those 29 turbines can generate up to 986 MW.

Environmental criticism

Relying on gas-fired generators brings environmental criticism with it. One commentator reacting to Anthropic's purchase argued that such generators are very bad for the environment and objected to the deal. Fast access to electricity does not erase the environmental cost of producing it, and Anthropic will have to confront the issue as it expands its energy infrastructure.

The power crunch is also pushing AI companies toward options other than new orders. Demand has grown for used and refurbished turbines and for retired jet engines converted to generate electricity. But those options come with limits, including maintenance needs, remaining service life and suitability for continuous operation. By taking over OnePWR's Caterpillar orders, Anthropic may be able to sidestep some of those obstacles.

Add as a preferred source on Google See Merhabyte stories more often in Top Stories on Google Search.

Comments

No comments yet. Be the first to comment.

Leave a comment

We do not ask for your e-mail. Comments are checked automatically before they go live.

Up next

All →